Investment activities
JSC “OGK-6” is carrying out investment activity along the following lines:
− implementation of large-scale investment projects;
− updating the existing industrial facilities.

Large-Scale Investment Projects
|
Project |
Increase of capacity (MW) |
Expected Project Cost |
|
“Addition of a gas turbine to Ryazanskaya GRES steam turbine plant No.7” (CCGT Unit-420) |
110 |
19 012 |
|
“Modernization of the condensing section of Kirishskaya GRES on the basis of combined cycle technology”, Unit No. 9 (CCGT Unit - 800) |
500 |
24 308 |
|
“Construction of Power Unit No. 9 using the circulating fluidized bed technology,” Unit No. 9 (330 MW) |
330 |
4 189 |
|
“Construction of the second phase of Cherepovetskaya GRES with separation of the first startup facility” – Unit No. 4 (330 MW) |
330 |
21 537 |
|
Total for the investment program |
1,270 |
69 046 |
Modernization of the Existing Industrial Facilities
According to the JSC “OGK-

Among the most important investment program projects are reconstruction of TFRM-500 current transformers, reconstruction of smokestack No. 2 at Ryazanskaya GRES, reconstruction of OSG – 110 kV electric facilities with installation of an automatic transformer and reconstruction of the water treatment plant (Chemical Treatment Plant-2) at Kirishskaya GRES, reconstruction of power unit No. 7 at Novocherkasskaya GRES and reconstruction of the fuel feed tunnel at Cherepovetskaya GRES.