Production

Eletricity and Heat Production 2007-2009

 

The total electric installed capacity of JSC “OGK-6” plants amounts to 9,162 MW. This renders JSC “OGK-6” the fourth largest company by installed capacity size among all WGCs and TGCs created as a result of the reform of electric power industry in Russia. The total installed heat of JSC “OGK-6” plants amounts to 2,704 Gcal/hr.

 

Plant

Installed electric capacity, MW

Installed thermal capacity (including water boilers), Gcal/hr

Geographic location

Primary/reserve fuel/starting fuel

Ryazanskaya GRES

2 650

180

Central UPS

Gas, coal / fuel oil / gas, coal

Novocherkasskaya GRES

2 112

75

South UPS

Coal / gas / gas, fuel oil

Kirishskaya GRES

2 100

1234

Northwest UPS

Gas / fuel oil / gas, fuel oil

Krasnoyarskaya GRES-2

1 250

1176

Siberia UPS

Coal / none / fuel oil

Cherepovetskaya GRES

630

39

Central UPS

Coal / gas / gas, fuel oil

GRES-24

420

-

Central UPS

Gas / none / none

Total:

9 162

2 704

 

 

 

Share price


Quotes are delayed according to exchanges regulations.
Powered by RUSTOCKS.com



Dialogue

Çàäàéòå âîïðîñ
ATS ÎÀÎ ÑÎ ÖÄÓ ÅÝÑ © 2007 JSC «OGK-6» All rights reserved  Ogilvy
© ÎÀÎ "ÎÃÊ-6"
Âñå ïðàâà çàùèùåíû